This construction video tutorial will
show the details of cement quota, brick work volume, number of fixes for a
brick wall construction.
To calculate the brickwork volume, just apply the
following formula :-
Total brickwork area x wall thickness
= 31.98 x 0.2 = 6.38 m3
= 31.98 x 0.2 = 6.38 m3
The ratio of cement & mortar
needed in brickwork is 1:3 (it can also be taken as 1:5 and 1:6).
Volume of brickwork = 6.38 m3
For 1 cubic meter of cement mortar, the volume of sand will be 0.2m3
For 6.38 cubic meter, the volume of sand will be 6.38 x 0.2 = 1.276 m3
Volume of brickwork = 6.38 m3
For 1 cubic meter of cement mortar, the volume of sand will be 0.2m3
For 6.38 cubic meter, the volume of sand will be 6.38 x 0.2 = 1.276 m3
For 1m3 cement mortar, the volume of
cement will be = (0.2x1440)/3 (3 denotes last digit of ratio)
= (0.2 x 1440)/3 = 96 KGS
For 6.38 cubic meter, the volume of cement will be 6.38 x 96 = 612.48 KGS
To
work out the number of cement bags, just divide it by 50 (as weight of 1 cement
bag is similar to 50 Kg)= (0.2 x 1440)/3 = 96 KGS
For 6.38 cubic meter, the volume of cement will be 6.38 x 96 = 612.48 KGS
Therefore, 612.48/50 = 12.24 bags = 13 bags (approx.)
Read more
~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~
No comments:
Post a Comment