How to analyze rate for brick masonry work

While analyzing the rate of brickwork, it is essential to ascertain the quantities of materials (bricks and mortar) and labors. There are different types of ratios for mortar which range from 1:2, 1:4, 1:6, 1:8 etc. Go through the following like to determine the quantity of mortar.
Estimating the quantity of bricks is necessary for the rate analysis.
Quantity Estimation for Brick Masonry - To analyze the rate of brick masonry, 1m3 of brick masonry is taken:
1. Number of bricks for 1 cubic meter of brick masonry:
For 1m3 of brick masonry, the number of typical size of bricks must be 494.
2. Quantity of mortar for 1m3 of brick masonry:
For 1m3 of brickwork, the quantity of the mortar should be 25 – 30%, i.e. 0.25m3 – 0.3m3 of cement masonry. For this purpose, cement mortar is selected as 0.3m3 .
Labor Estimation for Brick Masonry:
Labors which are essential for brick masonry belong to mason for brick work, labours for transmitting materials (sand, cement, bricks, and water), mixing and transporting mortar.
The quantity of labor is provided as requirement of labour in longer period for 1m3 of brick masonry.
1. Mason: The quantity of mason necessary for 1m3 of brickwork is provided as 0.94 days.
2. Labor: The quantity of labor for different types of works like carriage of materials, blending of mortar, carrying of mortar etc. are amassed. The labour necessary for 1m3 of brick masonry is for 1.57 days.
How to analyze rate for brick masonry work
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Monday, October 14, 2019

Some useful tips to work out the cutting Length of Bent Up Bar In Slab

For a site engineer, it is essential to work out the cutting length of bars based on the slab dimensions and provided instructions to the bar benders.
If the construction work is intended for the small area, the reinforcement detailing can be transferred to the bar benders. They will deal with the cutting length. But be careful that it may not be perfect as they do not consider the bends and cranks. They may provide some additional inches to the bars for the bends which are fully imperfect. Therefore, to get rid of this issue, a site engineer should try to compute calculate the cutting length independently.
In this article, detailed explanation is given for working out the length for reinforcement bars of slab.
The calculation is made on the following dimensions :-
Diameter of the bar = 12 mm
Clear Cover = 25 mm
Clear Span (L) = 8000
Slab Thickness = 200 mm
Development Length(Ld) = 40d
Process for computation
Cutting Length = Clear Span of Slab + (2 x Development Length) + (2 x inclined length) – (45° bend x 4) – (90° bend x 2)
Inclined length = D/(sin 45°) – dD/ (tan 45°) = (D/0.7071) – (D/1)= (1D – 0.7071D)/0.7071= 0.42 D
There exist four 45°bends at the inner side (1,2,3 & 4) and two 90° bends ( a,b ).
45 ° = 1d; 90 ° = 2d
Cutting Length = Clear Span of Slab + (2 X Ld) +(2 x 0.42D) – (1d x 4) – (2d x 2) [BBS Shape Codes]
Some useful tips to work out the cutting Length of Bent Up Bar In Slab
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Saturday, October 12, 2019

Some useful methods for estimating building works

The following method are useful for working out various building quantities like earth work, foundation concrete, brickwork in plinth and super structure etc.
a) Long wall – short wall method
b) Centre line method.
c) Partly centre line and short wall method.
a) Long wall-short wall method: Under this method, the wall along the length of room is treated as long wall whereas the wall that is situated vertically to long wall is called short wall. To find out the length of long wall or short wall, initially compute the length of centre line for separate walls. Then compute the length of long wall, (out to out) once half breadth at each end is added to its centre line length. Therefore, the length of short wall is calculated into in and is built by subtracting half breadth from its centre line length at each end. The length of long wall normally declines from earth work to brick work in super structure whereas the short wall enlarges. In order to obtain quantities, multiply these lengths with breadth and depth.
Some useful methods for estimating building works

~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Wednesday, October 9, 2019

Some useful tips to design a T-beam with the use of limit state method

This construction video briefly describes how to create the design of t-beam with the use of limit state method.
A T-beam (or tee beam) is applied in construction extensively. It is a structural element developed with reinforced concrete, wood or metal. It contains a t-shaped cross section that is formed by a stem and a flange of reinforced concrete or rolled metal.
The top of the t-shaped cross section acts as a flange or compression member in withstanding compressive stresses. The web (vertical section) of the beam underneath the compression flange contributes to withstand shear stress and offer better separation for the coupled forces of bending.
A T-beam has the capacity to tolerate large loads by providing resistance in the beam or by internal reinforcements. It operates similar to singly reinforced beam.
In order to enhance the structural strength of a T-beam, just utilize an inverted T-beam together with a floor slab or bridge deck linking the tops of the beams. If it is accomplished perfectly, the slab performs as the compression flange.

Some useful tips to design a T-beam with the use of limit state method
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Tuesday, October 1, 2019

How to prevent segregation of concrete

Definition of Segregation of Concrete?
Major components of concrete are cement, sand, aggregate, and water. Normally, a coating is made to concrete aggregate with cement and sand for developing the consistent mass disjointing of these constituent materials of concrete from each other. It is known as segregation of concrete.
Type of segregation:
1. Partition of course aggregate from the paste.
2. Partition of course agreement paste from the concrete.
3. Partition of water from the cement mix which is also known as bleeding.
The segregation contains unwanted properties in the hardened concrete. It also leads to honeycombing in concrete. Segregation also adversely impacts on stability, compressive strength and all other characteristics of concrete. It also results in forming cavities in the concrete surface.
Reasons for segregation:
The segregation mainly occurs due to the variation in specific gravity and size of its constituent material. Specific gravity of water is 1. Specific gravity of cement is approx 3.15 whereas that of aggregate is 2.6 to 2.7. Because of the variation in specific gravity, lighter particle goes upwards and heavier particle goes downwards and consequently the segregation of concrete occurs.
Other reasons range from greater water cement ratio in concrete. Besides, when excessive water is added at the time of mixing concrete, it results in segregation. Improper vibration for a long period on wet mix of concrete also causes heavy material to setting down and lighter cement sand paste to move upwards. Imperfectly proportioned mix and inappropriate placing on site may also lead to segregation.
How to prevent segregation of concrete
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Monday, September 30, 2019

Top 4 apps for civil engineering students

Civil Sutra: Civil Sutra is specifically created for the benefits of site engineers, site supervisor, contractors and Architects to supply crucial and useful information.
The app can be used for the following purposes :-
1. Quantity of concrete
2. Bricks quantity
3. Paint quantity
4. Mortar calculation for plaster
5. Unit Conversion Etc.
Civil Sutra can simplify the calculation and designing work with the use of standard tables and formulas. The civil engineers get rid of tedious manual calculation process on site and start automatic calculation with some simple clicks of the mouse.
Downoad (play.google.com)
My Civil CalC: This calculator can be used for rapid & precise unit conversion and calculation for area, volume, conversion with meter cube to meter feet, inch to mm etc.
It contains a unique feature of assigning measurement units feet-inch/ M/mm also with calculator to the input numbers and obtain the desired result together with the unit.
It is also possible to convert the calculated results to alternative units with different accessible converters at the bottom. It is very time saving and user friendly calculator toward the builders, civil engineers, architects, interior designers, estimators, contractors, billing engineers, store keepers. It also facilitates to covert the value with calculator.
Top 4 apps for civil engineering students

~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Friday, September 20, 2019

Some vital tips to control cracking with Reinforce Concrete Slab on Ground

Steel reinforcing bars and welded wire reinforcement are used to check crack width in nonstructural slabs-on-ground.
Most slabs-on-ground are unreinforced or minimally reinforced for crack-width control. If steel reinforcement is arranged in the upper or top portion of the slab thickness, it restricts the widths of random cracks resulting from concrete shrinkage and temperature restraints, subbase settlement, applied loads or other issues. This type of reinforcement is normally defined as shrinkage and temperature reinforcement.
Shrinkage and temperature reinforcement is not same as structural reinforcement. Structural reinforcement is generally arranged in the bottom section of the slab thickness to enhance the load bearing strength of the slab. Most structural slabs-on-ground contain both top and bottom layers of reinforcement for managing crack-widths and improving load capacities. Due to constructability issues and costs regarding two layers of reinforcement, structural slabs-on-ground are not regularly used as nonstructural slabs.
The basics: Steel reinforcing bars and welded wire reinforcement can’t control cracking. Reinforcement mainly remains inoperative unless the concrete cracks. Once cracking happens, it gets activated and manages crack widths by limiting the expansion of crack.
When the slabs are provided on greater quality sub bases with uniform support and include low shrinkage concrete with joints perfectly installed at a gapping of 15 feet or less, reinforcement is normally is not required. Seemingly, there exist few random or out-of-joint cracking. In case of random cracks, they should remain moderately tight due to the restricted joint spacing and low concrete shrinkage thus future serviceability or maintenance issues will be reduced.
If slabs are arranged on difficult sub bases with risks of non-uniform support or comprise of medium to high shrinkage concrete or joint spacing surpassing 15 feet, then reinforcement should be provided to control the widths of cracks. Since crack widths expand and become about 35 mils (0.035 inches), the effectiveness of load transfer via aggregate interlock is reduced and differential vertical movements over cracks or slab "rocking" can happen.
Due to this, crack edges remain uncover and edge spalling takes place, particularly when the slab is uncovered to wheeled traffic and especially hard-wheeled lift trucks. As soon as spalling begins, crack widths at the surface get expanded and slab deterioration along cracks is raised considerably.
When contraction joints are inappropriate and not installed, shrinkage and temperature reinforcement is necessary. This design approach is sometimes called as continuously reinforced or joint-less slabs and produces several closely spaced (3 to 6 feet) fine cracks all through the slab.
Crack control options: Normally, the cracks in slabs-on-ground are controlled with the following ways -
1) check the location of cracking by installing contraction joints (does not control crack widths) or 2) Installation of reinforcement (does not control crack location).
With Option 1, we can know where to crack in the slab and widths of contraction joints or cracks in the joints are mostly managed by the joint spacing and concrete shrinkage. When joint spacings and concrete shrinkage are raised, joint widths also expand. Similar to cracks, when joint widths turn out to be about 35 mils, the effectiveness of the aggregate interlock to transmit loads and resist differential vertical movements across joints is considerably decreased. Because of this, several load-transfer devices like steel dowels, plates or continuous reinforcement through contraction joints are used to keep positive load transfer and control differential vertical movements across joints.
With Option 2, the slabs are allowed to crack indiscriminately but crack widths are controlled through steel reinforcing bars or welded wire reinforcement. Normally, contraction joints are not installed with this option rather cracking happens indiscriminately that develop several, tightly held together cracks.
Some vital tips to control cracking with Reinforce Concrete Slab on Ground

~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~