Different types of BBS shape codes for steel

Sami Ullah, the renowned civil engineer, presents this useful video tutorial in civil engineering youtube channel. In this video, the detail process is given for finding out the quantity of steel as well as shape codes for the steel bars.

Shape codes are considered as the basis of a proper bar bending schedule.

While going to estimate the reinforcement detailing for various members concerning a building, small bent ups and other angle detailing should be considered in the calculation to produce valid and cost-effective bar bending schedule.

It will significantly reduce the cost and wastage of reinforcement.

In beams & slabs there exist various bent ups, cuttings, and development lengths. Each and every bend and angle presented in the member is the outcome of design calculation. Therefore, these should be carefully enforced in practice.

For small projects, it is unnecessary to compute these details, just include a few more inches and work out the Bar Bending Schedule.

Different types of BBS shape codes for steel

~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Thursday, December 19, 2019

Best Calculators Construction Engineers are Using

The construction industry is near the top of the most math-heavy fields of work. Each project starts guzzling out numerical data right from the very beginning of the process. All that information needs to be calculated using the proper tools to produce the desired result.
Chances are, you have been using some basic calculator to help in this work. A standard engineering calculator can be found in most civil engineers’ bags. Worse, we see that in modern days people are using the calculators in their mobiles in this task. However, if you are a construction manager worth your salt, you would know that these generalized tools are pathetic when it comes to handling complicated building-related data. Wouldn’t you wish there were calculators custom-built for construction jobs?
Fortunately, there are. Today, we will look into a few gadgets built specifically to handle the computational needs in a construction project. These calculators support custom functions, fractional computing, unit conversion, and a lot of other stuff specifically needed for building construction managers and civil engineers. Some of these are portable devices and some again are mobile apps. The 5 most popular construction calculators are:
1. Construction Master Pro
2. Construction Calculator-Building Material Estimate
3. Jobber 6
4. C-Calc Pro
5. Materials Estimating Calculator
Construction Master Pro: The flagship of Calculated Industries general construction calculation tools line, Construction Master Pro looks like any standard scientific calculator in a nice solid shockproof casing at first glance. Look closer, however, and you will see a myriad of custom functions and tools ornamenting the keypad.
Covering a wide range of constructional computation activities, this device can calculate details of building to framing to concrete work. Not only measurements, but you can also use this device to calculate how much material you need for building a given structure, the volume in excavations as well as fillings, and even go as far as counting the number of transports and their costs for your project.
The Construction Master Pro covers unit conversion needs as well, and unlike a scientific converter it will not needlessly bog you down into unnecessary unit lists. It can convert to and from all building standard units like foot, meter, inch, centimetre and so on. Another advantage this device offers is the conversion of not only lengths but also areas and volumes.
November 2019 Brings Eight Top Construction Projects in US
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Monday, October 14, 2019

Some useful tips to work out the cutting Length of Bent Up Bar In Slab

For a site engineer, it is essential to work out the cutting length of bars based on the slab dimensions and provided instructions to the bar benders.
If the construction work is intended for the small area, the reinforcement detailing can be transferred to the bar benders. They will deal with the cutting length. But be careful that it may not be perfect as they do not consider the bends and cranks. They may provide some additional inches to the bars for the bends which are fully imperfect. Therefore, to get rid of this issue, a site engineer should try to compute calculate the cutting length independently.
In this article, detailed explanation is given for working out the length for reinforcement bars of slab.
The calculation is made on the following dimensions :-
Diameter of the bar = 12 mm
Clear Cover = 25 mm
Clear Span (L) = 8000
Slab Thickness = 200 mm
Development Length(Ld) = 40d
Process for computation
Cutting Length = Clear Span of Slab + (2 x Development Length) + (2 x inclined length) – (45° bend x 4) – (90° bend x 2)
Inclined length = D/(sin 45°) – dD/ (tan 45°) = (D/0.7071) – (D/1)= (1D – 0.7071D)/0.7071= 0.42 D
There exist four 45°bends at the inner side (1,2,3 & 4) and two 90° bends ( a,b ).
45 ° = 1d; 90 ° = 2d
Cutting Length = Clear Span of Slab + (2 X Ld) +(2 x 0.42D) – (1d x 4) – (2d x 2) [BBS Shape Codes]
Some useful tips to work out the cutting Length of Bent Up Bar In Slab
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Saturday, August 24, 2019

Calculation Method of Concrete Quantity for a Staircase

In order to work out the quantity of a staircase, it is required to determine the concrete volume for the followings :-
• Steps and waist slab of 1st flight
• Steps and waist slab of 2nd flight, and
• Landing
Concrete volume for 1st flight of the staircase: The calculation is done based on the following dimensions :-
Riser = 6 inches
Tread = 10 inches
Length of a step = 4 feet
Number of steps = 9
The thickness of the waist slab = 6 inches
Concrete volume for the waist slab: To get the concrete volume for the waist slab, the inclined length of the waist slab be measured first. Inclined length of waist slab can be measured from the architectural plan.
The horizontal length of a waist slab is determined by,
=number of steps x tread
= 9 x 10”
= 7′-6”
The height of the landing top from floor is,
= number of riser x height of riser
= 10 x 6″ [number of riser = number of steps = 1]
= 5 feet
Therefore, the inclined length of the waist slab should be as follow :-
=√{(horizontal length)2 + (Height)2}
= (7’-6”)2 + (5’)2
= 9’ (round up)
Therefore, the concrete volume for the waist slab should be calculated with the following formula :-
= inclined length of waist slab x width of waist slab (width of a step) x thickness of waist slab
= 9’ x 4’ x 6”
= 18 cubic feet
Concrete volume for steps: Since steps come as triangular shape, so the volume of a step should be as follow :-
= ½ x tread x riser x length of a step
= ½ x 10” x 6” x 4
= 0.84 cubic feet
As there are 9 numbers of steps in a flight, therefore, the concrete volume for the steps of the first flight should be as follow :-
= 9 x 0.84
= 7.56 cubic feet
Therefore, the entire concrete volume for the 1st flight of the staircase should be computed as follow :-
= Waist slab concrete + steps concrete
= 18 + 7.56
= 25.56 cubic feet
Concrete volume for 2nd flight of the staircase: In case the 1st flight and 2nd flight are equivalent in drawing, the concrete volume will be similar. That is,
= 25.56 cubic feet
Concrete volume for the stair landing: The calculation is done on the basis of the following dimension :-
Length of landing = 8’-6”
Width of landing = 4’-6”
The thickness of landing = 6”
Therefore, the concrete volume for the landing will be as follow :-
= 8’-6” x 4’-6” x 6”
= 19.12 cubic feet
Therefore, the total concrete volume for the staircase should be as follow :-
= 1st flight concrete + 2nd flight concrete + landing concrete
= 25.56 + 25.56 + 19.12
= 70.24 cubic feet
Calculation Method of Concrete Quantity for a Staircase
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Monday, August 12, 2019

Calculation of buckling for pinned column

For the ideal pinned column, the critical buckling load is computed with Euler's formula:
                                                                                             Calculation of buckling for pinned column
Here:
E stands for Modulus of elasticity of the material
I stands for Minimum moment of inertia
L stands for Unsupported length of the column.
It should be remembered that irrespective of the end condition, the critical load is based not only on the material strength, but also on the flexural rigidity, EI. Buckling resistance is raised by enhancing the moment of inertia.
If a column buckles, it retains its deflected shape once the critical load is enforced. In most applications, the critical load is normally considered as the maximum load tolerable by the column. Theoretically, any buckling mode is feasible, but the column will ordinarily deflect into the first mode. A column will buckle when the load P attains a critical level, known as the critical load, Pcr.
For columns containing several types of support, Euler's formula may is useful when the distance L is substituted with the distance among the zero moment points. See "Effective Length Constant Table" below.
This length is known as the effective length Le and is demonstrated with the following equation:
Calculation of buckling for pinned column
The slenderness ratio is a vital parameter in the classification of compression members, and is demonstrated with the following equation:
Calculation of buckling for pinned column
Here:
r stands for Radius of gyration
I stands for Moment of inertia
A stands for Area cross section
If the slenderness ratio remains (greater than) critical slenderness ratio, then the column is considered as a long column and the Euler buckling formula will be as follow :-
If slenderness ratio remains less than the critical slenderness ratio, the column is considered as a short column.
Calculation of buckling for pinned column
In short columns, failure may happen by compression devoid of major buckling and at stresses surpassing the proportional limit. For this condition, Johnson's formula will be used :
Calculation of buckling for pinned column
For columns which collapse following the onset of inelastic behavior, the constant of proportionality should be utilized in spite of the modulus of elasticity (Engesser formula). The constant of proportionality, Et, refers to the slope of the stress-strain diagram beyond the proportional limit, known as the tangent modulus. Note within the linearly elastic range, E = Et.
To calculate column buckling, use the following online calculator engineersedge.com
Calculation of buckling for pinned column

~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Friday, May 24, 2019

Quantity Take-off in Earthwork Volume Calculation

Quantity Take-off software is also used in calculating Earthwork Volume and this earthwork is done to restructure the topography of a site to get the design levels.

There are various types of methods of volume calculation that can be approved to find earthwork quantities; there are various civil engineering projects like road work, irrigation canal project, tank survey, earth moving, etc. for which different calculation methods are used. Some of them are invented in many time ago when the computer or calculator were not invented and still now are being used. Besides this, nowadays industry practices of various kinds of volume calculation which are discussed here to help the readers to choose the right one.

Earthworks: These are engineering works made through the moving and/or processing of huge quantities of soil and unshaped rock. Earthwork is done to restructure the topography of a site to get the design levels. Earthwork includes cutting and filling to get the needed topography.

• Cutting: It is the procedure of digging earth material from a work location or borrows pits to reach the desired topography.

It is the procedure of moving the excavated material or extra earth material to work a location to reach the desired topography.

Applications of Earthwork: Earthwork is done in the projects like Road works, Railways, Irrigation project such as canals and dams, other common earthwork applications are land grading to reconfigure the topography of a site or to fix slopes. Method of Earthwork Calculation: There are four popular types of earthwork calculation which written below:

• Section method
• Average method
• Division by Square method
• Contour method


At first, an earthwork calculation survey needs to do on the site. During this survey, the site elevations of the existing at various points of the work site are stubborn. All the calculations are done depending upon these values.

Quantity Take-off in Earthwork Volume Calculation

Read more
~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Tuesday, May 14, 2019

Details about concrete cover in reinforcement

Concrete cover means the minimum distance among the surface of implanted reinforcement and the exterior surface of the concrete according to ACI 130 code. The concrete cover depth is calculated with a cover meter.

The purpose of the concrete cover is to safeguard the reinforcement.

While making design of reinforced concrete structures, the reinforcement already arranged is implanted in the concrete up to a specific distance from the face of the member due to the following grounds:

• To safeguard the reinforcement against corrosion.
• To make reinforcement as a good fire resistant.
• To arrange adequate entrenched depth in order to provide necessary stress to reinforcement.


This distance is calculated in several methods and recognized with various names:

1. Clear cover: It stands for the distance from the face of the member to the most exterior face of the reinforcement along with shear or torsion Stirrups or links.

2. Nominal cover: It has similarity as clear cover though with a dissimilar name. This term is applied with the code. It belongs to the distance calculated from the face of the member to the most exterior face of the reinforcement along with Stirrups or links. It is the dimension demonstrated in drawings and detailing.

3. Effective cover: It is the distance calculated from the face of the member to the center of area of the main reinforcement i.e. the tension or compression reinforcement. It refers to the dimension generally applied for design calculations.

Effective cover = Clear cover + (Dia of Stirrups/links) + 0.5 * (Dia of main reinforcement bars).

Also,
Effective cover = Overall depth – effective depth.


At each end of reinforcing bar, concrete cover should not be under 25 mm or less than twice the diameter of the bar.

For a longitudinal reinforcing bar in a column, concrete cover should not be under 40 mm or under the diameter of such bar. In case of columns with least dimension of 20 cm or under, whose reinforcing bars do no not goes beyond 12 mm, concrete cover of 25 mm should be applied for reinforcement.

For longitudinal reinforcing bars in a beam, the concrete cover should not be under 30 mm or less than the diameter of the bar.

For tensile, compressive shear or other reinforcements in a slab or wall, the cover should not remain under 15 mm or under the diameter of such bar.

For footings and other major structural members in which the concrete is arranged directly against the ground, cover to the bottom reinforcement should remain 75 mm. If concrete is poured on a layer of lean concrete, the bottom cover should be minimized to 50 mm.

Details about concrete cover in reinforcement

Read more
~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Monday, April 29, 2019

Types of water tank & the height calculation of tank

On the basis of material types and location, the water tank is categorized as follow :-

Chemical contact tank – This type of water tank is formed with polyethylene construction and prepared for retention time of chemical treatment.

Ground water tank – It is formed with lined carbon steel. The water is delivered through a water well or from surface water. A huge quantity of water is arranged in inventory and utilized throughout high demand cycles.

Elevated Water Tank – This type of water tank is also called water tower. It will produce pressure at the ground level outlet containing 1 psi per 2.31 feet of elevation. Thus, a tank that is raised to 70 feet develops about 30 psi of discharge pressure. 30 psi is ideal for most domestic and industrial requirements.

Vertical cylindrical dome top – This type of tank may reserve fifty gallons to various million gallons. These types of tanks are suitable for transport as their low-profile produces a low center of gravity facilitating to sustain equilibrium for the transport vehicle, trailer or truck.

A hydro-pneumatic tank – This type of tank generally refers to a horizontal pressurized storage tank. By pressurizing this reservoir of water, a surge free delivery of accumulated water can be provided to the distribution system.


On the basis of the shapes, the water tank is categorized as follow :-


Circular Tanks – They are most cost-effective and utilized in greater capacity for delivering water, sewerage treatment etc.

Rectangular Tanks – These types of tanks are utilized for small storage capacity and their construction process is expensive.

Spherical Tanks – These types of tanks are utilized for the cost-cutting measure and aesthetic view point.

Intze Tanks – They are suitable for greater storage capacity. In these types of tanks, domes are utilized as a substitute for level slabs.

How to find out the maximum daily demand necessary for the population of the locality?


Target Population = 1500
Maximum daily consumption
= 180% of average daily demand = 1.8 x q
The demand of water for domestic purpose = 200 lit / capita / day
Average daily requirement (q) = Per demand x Population
= 200 x 1500 = 3,00,000 lit / day
So, maximum daily demand = 1.8 x q litres / day
= 1.8 x 3,00,000 litres / day
= 540 x 103 litres / day
= 540 m3 / day

How to find out the complete height of the tank?


Suppose, the diameter of tank (D) = 12m (<30m)
Therefore, radius of tank (R) = 12/2 = 6m
Now, the volume of tank = 540 m3
The height of the cylindrical tank is taken as h
So, the capacity of tank = Ï€ x R2 x h

After deducting the values, we get the following :-


Ï€ x 62 x h = 540
or, h = 540 / (Ï€ x 36)
or, h = 4.77
So, the height of the cylindrical tank = 4.77 m
Suppose, free boarding = 0.25 m
Therefore, the total height of the tank = (4.77 + 0.25) = 5.02 m = 5 m (approx)

Types of water tank & the height calculation of tank

~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Wednesday, April 25, 2018

Steps to work out road filling in hilly area

S.L. Khan, the eminent civil engineer, presents another informative construction video tutorial where he briefly explains the process for working out the road filling in hilly area.

In this video, solution is given to the following examples :-


Examaple 1


With specified cross section of road in hill area, work out the quantity of earth work in banking toward the length of 100 ft.


Suppose the permission rate of the road is taken as breadth of the road and it is 32 feet. The half of it is 16 feet. The mean depth of the filling is taken as 1.85 feet. The side slope is taken as 2:1. The cross slope is taken as 10:1.


Based on the above data, the quantity of earth work in banking will be determined.


To obtain the total filling of this section, apply the following formula :-


Filling = Cross Section Area x Length


To learn rest calculation process, go through the following video tutorial.




~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Monday, April 23, 2018

How to measure prying force in bolted connection

This is another useful construction tutorial from Dr. Chirag Patel. In this video, you will learn how to make detail measurement for "Prying Force" in bolted steel structural connection as well as remove it’s effect.

In a tension or hanger connection, the operative load creates tension in the bolts and the bolts are designed as tension members. If the connected plate is admissible to deform, supplementary tensile forces known as prying forces are developed in the bolts.

In this video example is given for verifying the exact capacity of a D hanger connection based on the following dimension :-
Bolt Diameter = 30 mm
Bolt Grade = 4.6
Dimension of end plate = 230 x 150 mm
Thickness of T-flange = 32 mm
The connection will not collapse if the tension capacity is higher than total load. Here, tension capacity is taken as 200 kN.
To learn the detail calculation process, go through the following video tutorial.
How to measure prying force in bolted connection+

~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Tuesday, August 8, 2017

Details of technical specifications of bitumen macadam & bitumen concrete for any road work

This construction video briefly explains the technical specification for bitumen macadam and bitumen concrete essential for any road work.

Bitumen Macadam alias Asphalt Concrete is formed by blending aggregate, filler and bitumen and come in solid, medium or open graded on the basis of the end application.

Macadams are categorized into three primary layer categories like Base, Binder and Surface Course. It is applied as a binder course for roads where lots of heavy commercial vehicles pass through as well as a closed-graded premix materials exist with voids content 5-10 per cent. It has strong and long-lasting surface.
Bituminous concrete refers to a sort of construction material that is employed for paving roads, driveways, and parking lots. It is formed by mixing stone and other forms of aggregate materials combined jointly through a binding agent. This binding agent is known as "bitumen" and is a by-product of petroleum refining. It contains a dense, sticky texture like tar once heated, then develops a thick solid surface as soon as it gets dried. Bituminous concrete is also extensively recognized as asphalt in various parts of the globe.
This material does not include cement. It has typical black appearance. It is frequently placed right over a gravel base layer to build up new roads and parking lots, but may also be poured over prevailing concrete to patch-up or smooth out bumps and voids.
As soon as the bituminous concrete are poured onto the roadway, the surface is leveled and compacted through a large paving machines.
For Bituminous Macadam :-
1) Grade of bitumen should be vary from 60 to 70
2) Temperature at different stages :-
a) At the time of blending materials maximum temperature should be 1650C
b) At the time of laying, the temperature should be 1250C
c) At the time of rolling, the temperature should be 900C

3) Levels (tolerance) – At the time of rolling, the layers should be +6 M to -6 M.
4) Field Density Test – Here, compaction should be 98%; 1 test per 250 m2 of area.

To get the complete details, watch the following video.

Read Continue

~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co

~~~~~~~~~~~~~~~~~~~~~~~~

Saturday, March 18, 2017

Some useful construction tips to compute the sliding safety factor for cantilever retaining walls

This construction article is extracted from an exclusive article written by Javier Encinas, the renowned professional engineer Javier Encinas.
The article sheds light on how to compute the sliding safety factor for concrete or masonry cantilever retaining walls.
Retaining walls are specifically created to encircle soils among two dissimilar elevations. So, they have to primarily withstand the lateral pressures from the retained soil as well as any other surcharge. Cantilever walls are susceptible to sliding issues, specifically if constructed on inferior quality soils.
Cantilever retaining wall pressures
Pressures functioning on a retaining wall
Besides, to the retained backfill, retaining walls are dependent on surcharge loads at the top of retained mass. A surcharge belongs to a strip load. If the stem expands beyond backfill, the retaining wall has to withstand wind load. If the retaining walls are placed in seismic zones, the focus should also be given to seismic pressures.
The load has been used contains a definite effect on the wall. The backfill employs a triangular lateral pressure measured according to the equivalent earth pressure theory. The surcharge creates a constant rectangular pressure on the wall. The seismic pressure is trapezoidal, together with the greater pressure at the top. Due to the actions of these loads, a bearing pressure is created beneath the footing, as well as a passive pressure at the front of the wall.
Method for verifying the sliding failure mode
The wall will be moved to exterior by the horizontal pressures on the backfill side that will have a tendency to slide on its footing. The driving force from the assigned loads should be defied with an opposite friction force at the edge of the footing base and the foundational soil that is formed by the bearing pressure against the base.
Besides, the passive pressure against the front face of the wall and footing should also be taken into consideration. It will never happen that the natural soil will be unaffected throughout the construction, so usually the top portion of the soil cover for the passive force calculation is omitted.
To read the complete article, click on the following link
www.asdipsoft.com
sliding calculation

~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~


Wednesday, February 8, 2017

Variation among Working stress method and Limit state method

This construction video shows the variation among working stress method and limit state method.

The basic variance among Working state method (WSM) and Limit State method (LSM) is that WSM stands for an elastic design method while LSM stands for a plastic design method.

In elastic design method, the design strength is estimated in such a manner that the stress in material is controlled with its yield limit, under which the material adheres to Hooke's law, and therefore, the word "elastic" is utilized. This method is used to produce cost-effective design of simple beam, or other structural elements where the standard for evaluating the design is stress (static). But, in case of changing the evaluation standard to other factors like fatigue stress, both the methods will give similar design. Also, WSM substantially reduces the calculation efforts.

In plastic design method the stress in material is permitted to go outside the yield limit and move into the plastic zone to attain extreme strength. Therefore, the "moment-rotation" power of beam, as for instance, is applied for creating more cost-effective design. However, because of the deployment of the non-linear zone, this method comprises laborious calculation.

Given below, some other general differences:

1) Serviceability check if LSM is necessary since after the elastic region strain is greater, it leads to more deformation, therefore a check is required.
2) LSM refers to strain based method while WSM is stress based method.
3) LSM refers to non-deterministic method while WSM is deterministic approach.
4) Partial safety factor is applied in LSM while Safety factor is applied in WSM.
5) Characteristic values (resulting from probabilistic approach) are applied in case of LSM while Average or statistic values are applied in WSM.


~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
~~~~~~~~~~~~~~~~~~~~~

Thursday, September 24, 2015

Spreadsheet based calculation to model water flow in a double pipe heat exchanger

Douglas Price presents an video useful for the chemical engineering students. By undergoing this youtube video, one can learn how to make calculation through an excel based spreadsheet to model hot and cold water flow in double pipe heat exchanger.

The experimental and theoretical study of heat exchange is very vital for chemical and mechanical engineering students.

Temperature is characterized as the amount of energy that a substance contains. Heat exchangers can be applied for transmitting that energy from one substance to another. In process units, the temperature must be controlled for inward and outward streams. These streams range from either gases or liquids. Heat exchangers increase or decrease the temperature of these streams by transmitting heat to or from the stream.

The double-pipe heat exchanger refers to the most easiest types of heat exchangers. It is known as double-pipe exchanger as one fluid runs inside a pipe and the other fluid runs connecting that pipe and another pipe that encircles the first. Flow in a double-pipe heat exchanger is co-current or counter-current. There exist two flow configurations: co-current means when the flow of the two streams run in the identical direction, counter current means when the flow of the streams run in reverse directions.


Pipe Heat Exchanger Excel Calculation

~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
~~~~~~~~~~~~~~~~~~~~~~