How to measure minimum bar spacing for Bundle Bars in Cast-in Place Concrete as per AASHTO provisions

Minimum Bar Spacing: As per AASHTO LRFD, section 5.10, the minimum bar spacing for bundled bars should be measured on the basis of the acquired diameter rather than computing from individual diameters.

As for instance, if there are 2 nos. 32 mm dia bars, the similar diameter in accordance with 2×32 is 45mm. Therefore, 45 should be employed to utilize the following clauses from AASHTO.

For 2×32 dia bars, clear spacing should be provided as ~68mm for Cast-in Place concrete and 60mm for precast concrete.

Refer following Clauses from AASHTO LRFD 5th Edition 2010


5.10.3.1.1—Cast-in-Place Concrete
For cast-in-place concrete, the clear distance among parallel bars in a layer should not be under :
5 times the minimal diameter of the bars,
5 times the maximum size of the coarse aggregate, or 1.5 in.
5.10.3.1.2—Precast Concrete
For precast concrete fabricated under plant control conditions, the clear distance among parallel bars in a layer should not be under :
The minimal diameter of the bars,
33 times the maximum size of the coarse aggregate, or 1.0 in.
5.10.3.1.5—Bundled Bars
The number of parallel reinforcing bars bundled in contact to function as a unit should not go beyond four in any one bundle, apart from flexural members, the number of bars greater than No. 11 should not go beyond two in any one bundle.
Bundled bars should be attached within stirrups or ties. Individual bars in a bundle, cut off inside the extent of a member, should be abandoned at several points with minimum a 40-bar diameter stagger. Where spacing limitations are dependent on bar size, a unit of bundled bars should be considered as a single bar of a diameter taken from the corresponding total area.
How to measure minimum bar spacing for Bundle Bars in Cast-in Place Concrete as per AASHTO provisions
~~~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~~~

Tuesday, June 5, 2018

Basic differences between Development length and Lap Length

Development length is treated as specific minimum length of the bar that is needed on either side of a point of maximum steel stress, so as to transmit the bar force to encompassing concrete through bond devoid of slip, so that the bar is not pulled out under tension. Hooks, bends, mechanical anchorages are applied to supplement.

Lap length: When the steel is arranged in RC structure, if the necessary length of a bar is not suitably obtainable to produce a design length, then lapping is highly recommended.


Lap length stands for the least length that should have been arranged if two bars are attached together in order that forces are transmitted securely.
As for instance, while going to construct a tall column with height 100 feet. But, it is not possible to find a 100 ft long bar practically for caging. So, it is useful to slice the bars in each second story. Now, the tension forces are transmitted from one bar to the other at the location of discontinuity of bar.
Therefore, it is required to arrange the second bar nearer to the first bar that is suspended and overlapping should be provided. The amount of overlapping among two bars is defined as lap length.
LAP LENGTH IN TENSION.
1. For flexural tension – Ld or 30d either is larger.
2. For direct tension – 2Ld or 30d either is larger.
The straight length of lapping should not remain under 15d or 20 cm.
LAP LENGTH IN COMPRESSION: The lap length in compression should be similar to the development length in compression already worked out but not under 24d.
FOR DIFFERENT DIAMETER BARS: In case of bars with various diameter should have been cut off, the lap length is computed based on shorter diameter bar.
Article Source: quora.com
Basic differences between Development length and Lap Length

~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Monday, January 9, 2017

Detailed guidelines on Bar Bending Schedule of Beam

This construction video is based on Beam Reinforcement Details. By watching this video, one will be familiar with Bar Bending Schedule of Beam with some easy to follow processes.

Reinforcement in beam
The role of reinforcement is to withstand tensile stresses because of bending and shear in beams for singly reinforced sections. But some factors like architectural reasons or basement floors can limit the depth of section. Therefore, the beam section is designed as doubly reinforced to withstand tensile and compressive stresses and delivered with reinforcement in compression face.

Bar Bending Schedule for RCC Beam
Bar bending schedule is used to make the reinforcement calculation toward reinforced concrete beam. It presents the details of reinforcement cutting length, type of bends and bend length.

The following article will provide you more information on Bar Bending Schedule For RCC Beam. theconstructor.org


~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
~~~~~~~~~~~~~~~~~~~~

Friday, June 3, 2016

Specification Of Concrete Cover For Concrete Slab Design

Concrete cover for reinforcement is essential for safeguarding the rebar against erosion as well as fire. The depth of the cover is based on ecological conditions and type of structural member. The slightest thickness of reinforcement cover is specified in the drawings, or achieved from the related code of practice. The specifications for reinforcement cover for various structural members in diverse conditions are explained below :-

a) To each end of reinforcing bar, not below 25 mm or below twice the diameter of the bar.

b) In case of a longitudinal reinforcing bar in a column, not under 40 mm not less than the diameter of such bar. For columns of least dimension of 20 cm or below, whose reinforcing bards should not surpass 12 mm, a cover of 25 mm should be applied.

c) For longitudinal reinforcing bars in a beam, not under 30 mm or below the diameter of the bar.

d) For tensile, compressive shear or other reinforcements in a slab or wall not below 15 mm, not less than the diameter of such bar.

e) For any other reinforcement not below 15 mm, not less than the diameter of such bar.

f) For footings and other major structural members in which the concrete is placed directly alongside the ground, cover to the bottom reinforcement must be 75 mm. If concrete is discharged on a layer of thin concrete, the bottom cover is curtailed to 50 mm.

g) For concrete surfaces uncovered to the weather or the ground once forms are separated - like retaining walls, grade beams, footing sides and top etc. below 50 mm.

h) Expanded cover thickness is offered as specified on the drawings, for surfaces uncovered to the action of injurious chemicals (or uncovered to earth polluted by such chemicals), acid, alkali, saline atmosphere, sulphorone, smoke etc.