Thursday, July 3, 2014

How to estimate the cost of Material

Material Pricing

The price of the materials is calculated in two different methods:-

Lump Sum: It is a process to supply all the Materials in a group. As for instance a steel supplier may propose to provide all of the structural steel, steel Joists and roof deck for an approved price.

Unit Price: It is a system provided by the supplier to supply the materials at a price per unit.
A ready mix concrete supplier may recommend to deliver 3000 psi concrete to the project for a price of RM 110 per cubic yard.

Quantity TakeOff 


It is a procedure to find out the required construction quantities. It can be segregated into:-
  • Forecasting of the quantities of work
  • Working out of the prices related to those Quantities
Quantity TakeOff Procedures 

Classification of work item- for instance : Brick wall section or concrete footing.

Estimation of quantity varying from linear, area, volume and unit.

After calculating the material take-off, estimator can gather brief knowledge on the actual field procedure. Concrete take-off will commence from volume for footings, grade beams, slabs and slabs for ground floor etc.

Generally quantity quantity take-off is performed by the application of forms. In order to regulate the worksheets, provide accurately allocated areas in which proper information is to be submitted facilitating follow-up for smooth evaluation.

Pricing Materials  
It is a system for allocating a RM value for a work item following a projected specification and prearranged A process quantity needed.
  • After completion of quantifying of materials, the calculation of cost of materials should be started.
  • The pricing of each work item should consist of the individual subcomponents:-
  • Procurement of permanent and temporary materials
  • Labor needed for setting up the materials
  • Equipment necessary for shifting and installing materials
  • Other consumables, eg. Fuel and tools
Material Costs

In general, the amount of purchase = the unit price, which is recognized as quantity discount.
Freight cost should be taken into consideration and included in the direct cost of the materials. This is very important if the site location is very distant from nearby suppliers.

Other concerns for material procurement:
  • Quantity discount
  • Interest rate
  • Escalation
  • Holding cost
  • Credit facility
  • Allowance for method of measurement of the bill item
Material Pricing basis   
  • Published resources - Building Cost Indices
  • Company Cost records - an in-house record of accurate documenting and compiling company cost from earlier jobs
  • Vendor catalogues and quotations - prices are acquired directly from vendors from catalogues or indirect inquiries
  • While Upon assembling prices from vendor, the following points must be taken into consideration:
  • Payment requirements - cash, credit, credit term
  • Delivery charges
  • Lead time, product availability
  • Price guarantee
  • Quantity discount information
  • Price rise clause
 How to estimate the cost of Material 
~~~~~~~~~~~~~~~~~~~
Published By
Arka Roy
www.quantity-takeoff.com
~~~~~~~~~~~~~~~~~~~
 
 

Monday, June 16, 2014

Improve your project management and estimating skills with newly launched cloud based estimating & project management applications

Now-a-days various construction companies utilize high-tech mobile gadgets to handle their estimating and project management data in the cloud. Several new cloud based applications are emerging in the market to make the construction processes easy and uncomplicated.

Of late, Calif based Corecon Technologies Inc., www.corecon.com, launched Corecon Mobile for Apple’s iPhone and iPad. This latest application was designed to be applied with Corecon V7, a web based estimating, project management, and job-cost suite of construction software.
 
The Corecon Mobile application contains all of the tools included in the present version. Besides, it comes with superior functionality and an advanced user interface that is well matched with Apple’s iPhone or iPad capabilities.

The iOS platform has been totally redesigned and customized for construction site functions. The field associates will be able to snap development photos, revise checklist and punchlist items as well as import contacts from mobile gadgets straightway. Apple’s speech-to-text is also utilized with this newest application to copy out voice dictation into written or printed form if it becomes difficult to use text.

All of Corecon’s products are tied with a shared platform and this feature facilitates the field stuff to log daily as well as enter timecards directly in the iPhone/iPad application to be shown in Corecon V7 instantly.

So the mobile based application facilitates the project team members to grab a superior level of realtime project management by the application of smartphone and tablet appliances.

cloud based estimating and project management applications  
~~~~~~~~~~~~~~~~~~~~
Published By
Arka Roy
www.quantity-takeoff.com
~~~~~~~~~~~~~~~~~~~~

 

Friday, March 7, 2014

Special Interest Efforts to Subvert Energy Efficiency Bill in Federal Buildings Opposed by Groups

There is a new step in the approval process for developers who are looking to establish their business to Carrboro.


The American Institute of Architects (AIA) and more than 1,000 businesses around the country has asked the Congress to decline the special interest efforts to cancel the law setting goals for minimizing the use of fossil fuel in federal buildings by 2030.

The response is based on report regarding the incorporation of a repeal of Section 433 of the Energy Independence and Security Act, by the gas and oil lobby, in the bipartisan Shaheen-Portman energy efficiency bill.

The AIA CEO Robert Ivy, FAIA informed that the demand of removing federal energy laws through in the Shaheen-Portman bill by the fossil fuel industry is an unfortunate incidence. He also added that they are in support of the original bill with various admirable provisions as Sens. Shaheen and Portman has spent more than 2 years to craft a bipartisan energy efficiency bill. They cannot support the legislation that weakens the laws meant to support the federal government in saving taxpayers money by conserving energy.

The Senate Energy and Natural Resources Committee had earlier approved the bipartisan Shaheen-Portman bill that encouraged families, businesses and the government to conserve energy. It is still unknown if the revised bill advance any further in its current form. Ivy assured that they are committed to find a solution that would lead to the improvement of Section 433. But he also added that as long as the opponents ask for a complete repeal, the bill can probably not serve the interests of the public of America.

The design and construction companies in and around the country are designing buildings that meet and often exceed the present targets in Section 433. Due to Section 433, design companies are capable to generate new design strategies that are employed to support clients from private-sector to minimize their energy loads.

Special Interest Efforts to Subvert Energy Efficiency Bill

~~~~~~~~~~~~~~~~~~~~~~
published By
Tuhin Maity
www.quantity-takeoff.com
~~~~~~~~~~~~~~~~~~~~~~

Monday, February 24, 2014

Caterpillar Forecast Tops Estimates with the Recovery of Construction

One of the largest producers of mining and construction equipment, Caterpillar Inc. predict earnings for 2014 that has topped the estimate of the analysts as the recovery in the U.S. building industry stimulates the sale of excavators and bulldozers.

As the statement of the company, sales are expected to be about $56 billion with a plus or minus of 5%. The average of 13 estimates compiled by Bloomberg was $55.5 billion. Caterpillar jumped 5.9% to $91.29 in New York, which was considered the biggest profit since November 2011.

It is also expected that profit will be $5.85 per share, excluding $400 million to $500 million in restructuring costs, which is more than the estimate of $5.77 average. Illinois-based Caterpillar, Peoria, also confirmed approving a $10 billion share buyback plan through 2018 and will repurchase about $1.7 billion in stock in the first quarter that will mark its previous authorization.

The shares had dropped by 2.6% on January 24 in the midst of a general decline in equities. A selloff in developing-nation currencies led to concern that financial markets will be more unstable.

Caterpillar forecasts the growth of world economic by 3% in 2014, which is about 2% up from last year. It expects sales in its power systems and construction industries units to rise by 5%. Besides, it said that the resources segment, which includes mining equipment, will see revenue fall of about 10%. Caterpillar also added that the sales in construction industries rose by 20% in the fourth quarter as dealers did not cut inventory like last year and also the deliveries to customers in Latin America, North America and China escalated.


Caterpillar Forecast Tops Estimates with the Recovery of Construction

~~~~~~~~~~~~~~~~~~~
published by
Tuhin Maity
www.quantity-takeoff.com
~~~~~~~~~~~~~~~~~~~

Saturday, February 15, 2014

Decisive Political Support Required for Crossrail 2

It is often considered that the UK construction industry lacks expertise in managing risk on major infrastructure, and incurring high construction costs.


Like the High Speed 2 which is expected to the biggest infrastructure project in the country is facing an unforeseen expenditure of £14.4bn added upon its overall cost of £42.6bn. Though its leaders say that such contingency are not similar to expenditure, yet critics feel that if this added expense is taken away, a £28.2bn north-south link will certainly appear to be a lot more appealing.

As far as the proposed Crossrail 2 link is concerned, the Treasury expects a budget of almost £8bn for emergency situations for this scheme that is estimated to cost around £12bn. Strict and able guidance is required to reduce actions and incidents that could lead to uncertainty and cost inflation on projects. Detailed design and precise cost estimation can minimize the cost of Crossrail 2 as it is in its initial stage.

Decisive political support is required to continue with the scheme of Crossrail 2 to ensure that designers and contractors can work on minimizing its risks and overall cost.

The London rail capacity is expected to be full at the seams when Crossrail 2 opens in the latter part of this decade. Only then the ordinary Londoners may find the advantage of having its building sites on their doorsteps.

Decisive Political Support Required for Crossrail 2

~~~~~~~~~~~~~~~~~
published by
Tuhin Maity
www.quantity-takeoff.com
~~~~~~~~~~~~~~~~~~

Thursday, October 31, 2013

Post River Software introduced Asphalt Pro mobile applications for asphalt contractors

Post River Software introduced Asphalt Pro mobile applications. It is free and useful for professional asphalt contractors and inspectors to examine and quality control in the job site through smartphone technology. The tool consists of standard material and cost estimator as well as a complete set of tools to go with workflow and inspection practices for field application. These may range from mix yield underrun/overrun calculators, tack and seal distance calculators & rate validators; and visualizers to balance plant, truck, paver and roller capacities.

The one of the most important features of Asphalt Pro app is the Balanced Production Tool. It facilitates to provide a persistent pour of mix to the paver. The Seal Application tool comes up with a productive way for shot distance computation and rock lands for sealcoat processes. It has also the to validate those rates once the seal has been positioned. The application also contains project documentation capabilities. The project team will be able to detect any problem associated with a project, snap a photo and include a description as well as a station location. For confirming exactness, every photo is GPS and time stamped.

Go through the following link to download the application www.itunes.apple.com

The Asphalt Pro application contains the following exclusive features:-
  • Cost Estimator for small projects, parking lots and change orders
  • Work out Mix Yield and make a comparison to project estimates to detect overruns or underruns
  • Compute Tack and Seal distances facilitating application operations as well as validating rates for inspection duties
  • Modify any parameters for better production, enhance efficiency and minimize constraints
  • Snap, arrange and distribute digital images of issues associated with the project with GPS and time coding
  • Contains six conversion calculators containing units for every value required by a contractor and inspector in the jobsite in both US and Metric
  • All calculations can be sent back to the office through email for documentation, updating supervisors or for general project record keeping
  • Cost Estimator for small projects, parking lots and change orders
  • Each function has a help screen to assist users

    ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
    Published by 
    Rajib Dey
    Content Writer
    www.quantity-takeoff.com (Get all types of estimating sheets, softwares, directory, news, building codes)

Tuesday, October 29, 2013

Demonstration of Construction Estimating Technology at Site Prep Tech Seminar by Maxwell System

Maxwell Systems, Inc., a solution provider in construction software, has just declared that Michael Gillum, Director of Product Management; Estimating at Maxwell Systems and Daniel Frondorf, CPE, Chief Estimator at DG Frondorf and Associates LLC, will participate in site prep tech and deliver messages on the topic “Getting Up to Speed on Estimating and Bidding - Panel and Q&A”. Both will also focus on why should site prep contractors have thorough knowledge in precise bidding process. Site prep tech is the first ever construction technology seminar catering to site preparation contractors, engineers and businesses who appoint them.

DG Frondorf contains vast experience in using Maxwell Systems estimating software for 12 years. He will demonstrate how he has successfully utilized the software in his professional life to build up and produce a considerable amount of project data in the quickest possible time.





The participants of this event can also gather knowledge on how to control bidding and estimating software for providing quicker and more precise takeoffs as well as bidding, and deal with superior workflows.

The event is scheduled to be held on Wednesday, November 6 at 1.45-2.30 pm.

In order to book your seat, visit the following link sitepreptech.com

~~~~~~~~~~~~~~~~~
Published by 
Rajib Dey
Content Writer
www.quantity-takeoff.com (Get all types of estimating sheets, softwares, directory, news, building codes)

Friday, September 13, 2013

Substantial growth and opportunities for Florida contractors with the Construction Management Development Program

Construction Estimating Institute (CEI), who offers construction training programs nationwide, had acquired a contract with the Florida Department of Transportation (FDOT), to initiate the Construction Management Development Program (CMDP) and Bond Guarantee Program (BGP). The programs are intended for small businesses and Disadvantaged Business Enterprises (DBEs), who are looking for bid and executing construction work, to give them proper training and assistance.

The training will commence on Tuesday, September 24th in Orlando, repeated on Thursday, September 26th in Fort Lauderdale with the launch of “Your Road to Working with FDOT” seminars. Attendees will acquire knowledge on how to make their companies get ready to participate in competitive bidding on FDOT construction projects.


By attending this seminar one can learn how to bid public work, finding jobs in your area, gaining access to the FDOT website as well as achieving FDOT backed bonds. There will be also arrangement for training towards small businesses in the arena of plan reading and estimating, constructing and submitting bids, project planning and scheduling, and elementary business operations.

In order to register your seat, contact with CEI at phone: 1-800-423-7058, fax: 1-941-346-0221

~~~~~~~~~~~~~~~~~~~~~

Published by 
Rajib Dey
Content Writer
www.quantity-takeoff.com (Get all types of estimating sheets, softwares, directory, news, building codes)

Thursday, September 5, 2013

The InBusiness Estimating Module is a helpful software application for construction estimators

COMSS Limited, a renowned name construction software application, has just introduced  InBusiness Estimating Module approved by the Construction Industry Federation (CIF). It is a lean software application that is very useful for building estimator as it enhances the replication of estimating building costs within a clear & a modern interface with its streamlined workflow.  
InBusiness Estimating Module can calculate building cost estimations rapidly & precisely which facilitate construction estimators to participate in the bidding process for various projects and increase the profitability. The estimators can get clear cut ideas about the prices for bidding and the obtainable margins.
The software contains the following exclusive features :-
The data contained in an estimate are accessible to other modules all through the construction phase which result in easy monitoring of costs against what has been promised to the customer.
InBusiness Estimating provides solution for post-contract valuations and variations facilitating users for getting superior ideas regarding project profitability all through the construction stage Which enhances the control over business profitability.
InBusiness Estimating software is useful for various types of professionals. It contains an option to Plug Rates allowing users to get rid of inserting detailed item breakdowns and price more jobs instantly.
The software offers authenticated information related to resource costs from the estimate to completion of the job. The incorporated Construction suite presents a report that compares completed work in a Valuation stage depending on the original Estimate, and measures up to the real costs.

The software can be purchased 20% discount off the subscription price for the initial two years and the first 20 companies will eligible to get the offer which buy it prior to September 30, 2013.
The users can buy the software as a permanent license or on a yearly basis. If any user subscribes for the license they don’t have to any upfront payment for licenses.
Supplementary modules can be included in the license at any time throughout the subscription period. Available as a standalone module, InBusiness Estimating adds even more value when integrated with the InBusiness Construction Software Suite.

Apply online for getting a demo version http://www.comss.org/schedule-a-demo/
~~~~~~~~~~~~~~~~~~~
Published by 
Rajib Dey
Content Writer
www.quantity-takeoff.com (Get all types of estimating sheets, softwares, directory, news, building codes)

Friday, August 2, 2013

Benchmark Estimating Joins hand with the Viewpoint Construction Software Development Partner Program

Viewpoint Construction Software® and Australia-based Benchmark Estimating, a key developer of world class estimating software, just declared an alliance that will be useful for customer communities to avail the opportunity of superior technological solutions covering a wide array of the construction lifecycle roadmap. 

Benchmark Estimating provides a series of solutions for making the estimating processes more organized and for incorporating with other business processes. This incorporation facilitates users to obtain improved productivity and efficiencies which result in precise and cost-effective estimates.

Both the companies will extend their partner program to Australian providers in order to put value and functionality to customers in all the regions. This partnership will help the customers to find out their exact profit margin by getting more jobs.
This collaboration will great benefits to the customers through the globe with improved estimating, progress measurement, and forecasting with improved accuracy.

~~~~~~~~~~~~~~~~~~~~~~~~~~~
Published by Rajib Dey
Content Writer
www.quantity-takeoff.com (An information hub for construction estimating)

Like us on facebook