Steps involved in cement concrete works

Given below, brief specifications for executing cement concrete works for different objectives :-

1. Materials for Cement Concrete: Different types of materials cement, aggregates and water are required for cement concrete works. The aggregates are categorized as fine aggregates (sand) and coarse aggregates. The aggregates should comprise of inert material and should be clean, dense, hard, robust, long-lasting, non-absorbent. Besides, it should have the ability to make superior bond with the cement mortar.

Cement - Fresh Portland cement or pozzolana Portland cement (PPC) should be used according to requirement or specification and should contain the necessary tensile and compressive strength and fineness.

Fine Aggregates - Course sand with hard, sharp and angular grains should be utilized as fine aggregate or sand and it should get through 5mm (3/16”) square sieves or mesh. It should contain standard quality and does not contain dust, dirt and organic matters. Sea sand is not recommended for concrete works. Fine aggregates should comprise of crushed stone or manufactured sand if indicated.

Coarse Aggregates - These should comprise of hard broken stone of granite or similar stone and does not contain dust, durst and other foreign materials. The size of stone ballast should remain 20mm (0.75 inches) and less and should be arranged on 5mm (0.25 inch) square mesh. These should be well grades to retain voids under 42%.

The size of coarse aggregate is based on the thickness of concrete and nature of work. As for instance, size of coarse aggregates for building works should remain 20mm and 40mm to 60mm sizes are applied for road work and mass concrete works.

Water - The quality of water should be same as drinking water and it does not contain alkaline and acid matters.

2. Proportioning of Cement Concrete: The proportions in cement concrete should be according to the design and strength requirements. The proportion can be 1:2:4 (M15 concrete) or 1:1.5:3 for M20 concrete. The proportions of 1:2:4 concrete include the ratio of cement: sand: coarse aggregates by volume until indicated. Least compressive strength of concrete of 1:2:4 mix proportion should be 140 kg/sq.cm or 2000 lbs/sq.in on 7 days.

3. Measurement of Materials: Sand and coarse aggregates are calculated by volume with boxes. Cement should not be calculated by box, one bad of cement of 50kg weight should be treated as 1/30 cu.m or 1.2 cu.ft volume. Size of measured boxes may be 30 cm x 30 cm x 38 cm or 35 cm x 35 cm x 28 cm similar to the content of one bag of cement.

All materials should be dry and in case of utilizing damp sand, compensation should be done with extra quantity sand to the extent necessary for bulking of sand.

4. Mixing of Cement Concrete: Mixing of concrete should be done with machine to attain superior quality. For small works, hand mixing by batches is suitable.

5. Checking for Concrete Slump: Slump test should be conducted constantly to control the addition of water and to retain the desired consistency. A slump of 7.5cm to 10 cm (3 inches to 4 inches) is perfect for building work and 4 cm to 3 cm (1.5 inch to 2 inches) is ideal for road work.

6. Formwork for Concrete Works: Formwork centering and shuttering should be arranged as per need and the standard specifications prior to place concrete to confine or to support or to retain the concrete in exact location. The inside surface of the concrete should be oiled with formwork oils so that the concrete can’t stick to it.

Before placing concrete, water should be sprinkled over the base and formwork where the concrete will be arranged. Forms should not be detached prior to 14 days in general, side forms may however be detached after 3 days of concreting.

7. Placing of Concrete: It is necessary to place concrete gently in layers not surpassing 15cm or 6 inches and it should be consolidated by pinning with rods and tamping with wooden tampers or with mechanical concrete vibrating machines unless a solid concrete is produced.

Concrete should be placed constantly. If the placing of concrete is postponed for rest of the day or for the following day, the end should be sloped at an angle of 30 degrees and made rough for jointing again.

Curing of Concrete: After about two hours of placing when the concrete starts to become solid gradually, it should be retained moist by covering with wet gunny bags or wet sand for 24 hours and then curing by flooding with water making mud walls of 7.5 cm or 3 inches high or by covering with wet sand or earth and kept damp constantly for 15 days.

Steps involved in cement concrete works

Read more
~~~~~~~~~~~~~~~~~~~~~~~~
Published By
Rajib Dey
www.constructioncost.co
~~~~~~~~~~~~~~~~~~~~~~~~

Friday, March 8, 2019

Steps included in concrete manufacturing

The concrete quality depends on the manufacturing process of concrete. The manufacturing process involves the following steps :- Batching or measurement of materials, Mixing, Transportation, Placing, Compacting, Curing.
Batching of Material: To maintain the standard of concrete, the quantities of the materials should be perfect. The cement, aggregates and water should have utilized along with 3 percent of batching quantity and the admixture along with the 5 percent of batching quantity. Generally, two types of batching like the volume batch and the weight batch are utilized. The selection of batching method is influenced by the size of job, necessary production rate, and required standards of batching performance.
Volume Batching: Volume batch is suitable for the small works only. The amount of concrete materials is calculated with loose volume by means of standard box alias volume gauge box made of wood or metal. The amount of solid granular material in a cubic meter will be considered as an indefinite quantity. As for instance, the volume of moist sand in a loose condition weights much less as compared to the identical volume of dry compacted sand. Cement is calculated with weight in spite of the methods of batching. The cement is always calculated in terms of weight. The volume of one bag cement (50 kg) is 0.035 m.
Weight Batching: For all types of larger works, weight batching is recommended. There are several types of weight batches.
For small works, manually weight batch is ideal. All the materials are calculated manually by weight. The weight is taken in ordinary weight platform machine. The buckets are applied for large works. The bucket releases the materials directly into the mixture machine. For small to large works, manually or electrically operated automatic batching plants are used.
Mixing: The strength of the concrete relies on the mixing of materials. Standardized mixing process allows to mix the cement to aggregates in a proper way. There should be a coating of cement past on all the aggregate particles and all the materials of the concrete should be mixed into a homogeneous mass when the mixing is performed either by hand or machine.
Transportation of concrete: The concrete can be transported either by normally of mechanically. The concrete is transported manually through pans, wheel carts for small works whereas for large and enormous works, the concrete is transported through buckets or by pumps controlled mechanically.
Placing of concrete: Placing of concrete means arranging the concrete in its desired position. Concrete should be set in position in a perfect way as rapidly as possible within the initial setting time of the cement. Occasionally, admixture is utilized to raise the initial setting time.
Compaction of concrete: Compaction stands for the method for elimination of air voids from the concrete since air voids in concrete creates the vacuum and it reduces the concrete strength significantly. Compaction is performed manually or mechanically. The damping rods are employed in manual system. In mechanical process, vibrators are utilized. The manual compaction system is effective for small size of works. The vibrators are recommended for large size works. Vibrators are categorized into three types, internal vibrators, external vibrators and table vibrators.
Curing of concrete: Curing is vital for strength development and stability of concrete. Curing is started right away after placing and finishing of concrete, and entails maintenance of desired moisture and temperature conditions, both at depth and adjacent to the surface, for elongated periods of time. Properly cured concrete contains a sufficient amount of moisture for continued hydration and formation of strength, volume stability, endurance to freezing and thawing, and abrasion and scaling resistance.
For ordinary Portland cement, the period of curing time is from 7 days to 14 days. In case of rapid cement, the curing time is decreased.